Increase in payment disputes is a trend seen in construction industry over the past couple of years. There are varieties of reasons for the dispute; it can be simple disagreements about the scope of work in a contract, to a party leaving its subcontractors with no payment and little remedies. One of the common issues in the construction industry is changes brought to scope of work during construction. Such changes result in additional costs to the contractor.
In a situation where a contractor requires performing additional work due to changes ordered by the owner, the contractor is entitled to additional costs incurred in performing such works. Usually, the contract between the parties would have a clause for an equitable adjustment in contract price for certain changes. Recoverable extra costs may include the costs of material, labor, subcontracts, overtime, and additional equipment.
If extra work is not covered in the contract, the contractor also may recover in quantum meruit for the reasonable value of services and material benefits provided to the owner. Quantum meruit is a method used to determine the exact amount owed to a person. A court may measure this amount either by determining how much the defendant has benefited from the transaction or by determining how much the plaintiff has expended in materials and services.
Some courts may allow quantum meruit recovery for extra cost even when a contract exists fixing a price. In S. Bell Tel. & Tel. Co. v. Acme Elec. Contractors, 418 So. 2d 1187 (Fla. Dist. Ct. App. 4th Dist. 1982), it was held by the District Court of Appeal of Florida that defendant corporation was obligated under an implied contract to pay plaintiff for the additional work plaintiff performed in addition to the amount stipulated in the original contract.
Every contractor has to take certain steps to ensure prompt payment on their contracts. When you enter in to a contract with a company it is better to inquire in to how it operates, its financial stability, its track record of making payments, how it handles change orders, etc. You should be a little more diligent and more selective with whom you worked. It is better to enter into a contract with a developer, general contractor, or subcontractor you are familiar with or you feel completely comfortable to work with.
It is always safe to execute surety bonds to protect the investments you make in construction industry. Sometimes a party simply cannot or will not make payments for various reasons. Payment bonds are very important in such a situation to get payments for the work done. Mechanics liens are also one of the easiest ways to ensure payment on a construction project. A contractor has to file liens promptly within the limitation period. Limitation period varies from state to state, but generally, a contractor must first issue a notice to the original contractor and property owner within a couple months of the work or materials being furnished. They must also file a lien affidavit with the county clerk of the county in which the property is located.
When additional work is performed, send out regular notices every month. Send a demand letter for the amount owed and if possible send a lawyer’s notice which helps in conveying the message that you are serious. Take appropriate steps to protect your interests promptly and diligently.
Sources: